Indoor Pool Update
Following the recent demolition of the indoor pool deck, it was discovered that the existing drainage system is severely corroded and beyond repair. As a result, a full replacement of the system is necessary, which requires involvement from a mechanical engineer and the acquisition of city permits. We are currently awaiting our permits from the city before the project can be completed. Once these permits are received, the project is anticipated to take 6-8 weeks to complete.
A further update on a reopening date will be provided to members once the required permits have been obtained. We are currently estimating a reopening date sometime in September. Our staff is actively coordinating with the pool contractor to expedite the process and ensure that the upgraded facility is completed as efficiently as possible.
We look forward to welcoming our members back to an improved indoor pool experience soon!